Summary · Updated 17 November 2026
Australian Data Centre Pipeline: Projects by State and Stage
As of 17 November 2026, DC Info tracks 121 data centre projects in Australia: 21 under construction, 21 approved, 60 planning, 17 operational / expansion, 2 other. 92 of 121 projects publish a capacity figure in MW, together about 32.11 GW as published. Bases differ (IT load, total facility, grid connection, generation), so treat this as an indicative scale; each record shows its basis (capacity definitions). New South Wales has the most projects (48). Separately, the directory lists 185 data centre facilities.
Data centre projects by state
| State / territory | Projects | Under construction | Published capacity | Facilities |
|---|---|---|---|---|
| New South Wales | 48 | 9 | 10.70 GW | 59 |
| Victoria | 40 | 7 | 9.69 GW | 31 |
| Queensland | 9 | 1 | 1.98 GW | 29 |
| Western Australia | 5 | 1 | 1.18 GW | 28 |
| South Australia | 6 | 0 | 4.30 GW | 18 |
| Australian Capital Territory | 6 | 1 | 816 MW | 12 |
| Northern Territory | 3 | 1 | 3.01 GW | 4 |
| Tasmania | 4 | 1 | 424 MW | 4 |
| Australia | 121 | 21 | 32.11 GW | 185 |
Projects by stage
| Stage | Projects | Published capacity |
|---|---|---|
| Under construction | 21 | 2.96 GW |
| Approved | 21 | 2.20 GW |
| Planning | 60 | 25.67 GW |
| Operational / expansion | 17 | 1.27 GW |
| Other | 2 | — |
“Operational / expansion” is a project stage (an operating site being expanded); data centre facilities are listed separately.
Largest Australian data centre projects by published capacity
| Project | Owner / operator | State | Stage | Capacity |
|---|---|---|---|---|
| Victorian AI Hub | Syncline Energy | VIC | Planning | Up to 2.4 GW Basis not stated |
| Beetaloo Digital Weddell precinct | Beetaloo Digital (Beetaloo Energy Australia, ASX:BTL) | NT | Planning | Up to 2 GW Generation |
| Western Downs Digital Park | Zerra DC (with Australian Data Centres and Macquarie Capital) | QLD | Planning | Up to 1.44 GW IT load |
| CDC Kemps Creek (third Sydney campus) | CDC Data Centres | NSW | Planning | 1.4 GW Total facility |
| CDC Ashfords Road Data Centre, Gregadoo | CDC Data Centres | NSW | Planning | Up to 1.4 GW Total facility |
| Firmus Stirling North AI Factory | Firmus Technologies | SA | Planning | ~1.3 GW IT load |
| Mamre Road Data Centre Campus | ISPT (AirTrunk named prospective buyer, conditional) | NSW | Planning | 1.2 GW Basis not stated |
| Tungkillo Compute and Energy Hub | Quantum DC | SA | Planning | ~1.2 GW Basis not stated |
| NEXTDC M5 Melbourne | NEXTDC | VIC | Planning | ~1.2 GW Total facility |
| Firmus Tailem Bend AI Factory | Firmus Technologies | SA | Planning | ~1 GW IT load |
| Project Ares (Energy North) | Energy North | NT | Planning | 1 GW IT load |
| Project Meridien | Gingerah Energy consortium | WA | Planning | Up to 1 GW IT load |
| IREN Redbank campus | IREN | NSW | Planning | Up to 900 MW Total facility |
| STACK MEL03 Tarneit | STACK Infrastructure | VIC | Approved | 864 MW Basis not stated |
| IREN Bundey data centre campus | IREN | SA | Planning | 800 MW Basis not stated |
Ranked by the published MW figure; bases differ (shown next to each figure). See capacity definitions and largest data centres in Australia.
Frequently asked questions
- How many data centre projects are there in Australia?
- As of 17 November 2026, DC Info lists 121 data centre projects in Australia (21 under construction, 21 approved, 60 planning, 17 operational / expansion, 2 other), plus 185 data centre facilities. The directory is updated regularly and is not a complete census.
- Which Australian state has the most data centre projects?
- New South Wales, with 48 of the 121 projects in the DC Info directory as of 17 November 2026. Victoria 40; Queensland 9; South Australia 6; Australian Capital Territory 6; Western Australia 5; Tasmania 4; Northern Territory 3.
- How many data centres are under construction in Australia?
- 21 of the 121 projects in the DC Info directory are listed as under construction as of 17 November 2026.
- What is the largest data centre project in Australia by published capacity?
- In the DC Info directory, the largest published capacity figure is 2.40 GW (basis not stated) for Victorian AI Hub (Syncline Energy, Victoria), as of 17 November 2026. Capacity bases differ between projects, so rankings are indicative only.
- How is the DC Info data compiled?
- Records are researched from company announcements, planning documents, operators’ own facility information, industry information and news reports. Each record shows the date it was last checked; unknown values are left blank, and unconfirmed leads are labelled ‘Unverified – needs further confirmation’ on their record pages. Original source links are available to members; a source can be requested via the contact page.
Data centres by state
All figures are generated from the DC Info directory (last updated 17 November 2026). To cite: “DC Info, Australian data centre directory, dcinfo.com.au, accessed 17 November 2026”. See methodology.