As of 17 Nov 2026, the largest Australian data centre project in the DC Info directory by published capacity is Victorian AI Hub (Syncline Energy, VIC) at Up to 2.4 GW (basis not stated). The largest data centre facility by published IT capacity is NEXTDC M3 Melbourne at 225 MW.

Largest data centre projects by published capacity

Largest Australian data centre projects
ProjectOwner / operatorStateStageCapacity
1Victorian AI HubSyncline EnergyVICPlanningUp to 2.4 GW Basis not stated
2Beetaloo Digital Weddell precinctBeetaloo Digital (Beetaloo Energy Australia, ASX:BTL)NTPlanningUp to 2 GW Generation
3Western Downs Digital ParkZerra DC (with Australian Data Centres and Macquarie Capital)QLDPlanningUp to 1.44 GW IT load
4CDC Kemps Creek (third Sydney campus)CDC Data CentresNSWPlanning1.4 GW Total facility
5CDC Ashfords Road Data Centre, GregadooCDC Data CentresNSWPlanningUp to 1.4 GW Total facility
6Firmus Stirling North AI FactoryFirmus TechnologiesSAPlanning~1.3 GW IT load
7Mamre Road Data Centre CampusISPT (AirTrunk named prospective buyer, conditional)NSWPlanning1.2 GW Basis not stated
8Tungkillo Compute and Energy HubQuantum DCSAPlanning~1.2 GW Basis not stated
9NEXTDC M5 MelbourneNEXTDCVICPlanning~1.2 GW Total facility
10Firmus Tailem Bend AI FactoryFirmus TechnologiesSAPlanning~1 GW IT load
11Project Ares (Energy North)Energy NorthNTPlanning1 GW IT load
12Project MeridienGingerah Energy consortiumWAPlanningUp to 1 GW IT load
13IREN Redbank campusIRENNSWPlanningUp to 900 MW Total facility
14STACK MEL03 TarneitSTACK InfrastructureVICApproved864 MW Basis not stated
15IREN Bundey data centre campusIRENSAPlanning800 MW Basis not stated
16Keppel Morwell AI data centre campusKeppelVICPlanning720 MW Total facility
17NEXTDC S7 Sydney (OpenAI MoU)NEXTDC; OpenAI MoU (non-binding)NSWPlanning612 MW Basis not stated
18CDC Hume Campus 3CDC Data CentresACTPlanning576 MW Basis not stated
19AirTrunk Kurri Kurri Data CentreAirTrunkNSWPlanning550.5 MW Basis not stated
20CDC Marsden Park campusCDC Data CentresNSWUnder construction504 MW IT load

Ranked by the published MW figure; the basis is shown next to each figure and bases differ. Most of these are proposals; stage matters. See capacity definitions.

Largest data centre facilities by IT capacity

Largest data centre facilities by IT capacity
FacilityOperatorStateIT capacity
1NEXTDC M3 MelbourneNEXTDCVIC225 MW
2NEXTDC M2 MelbourneNEXTDCVIC120 MW
3Dataspace Greystanes Data CentreDataspaceNSW92 MW
4NEXTDC S3 SydneyNEXTDCNSW80 MW
5NEXTDC S2 SydneyNEXTDCNSW30 MW
6Dataspace Noble Park Data CentreDataspaceVIC28 MW
7NEXTDC P2 PerthNEXTDCWA20 MW
8NEXTDC S1 SydneyNEXTDCNSW16 MW
9NEXTDC M1 MelbourneNEXTDCVIC16 MW
10NEXTDC S6 SydneyNEXTDCNSW14 MW
11NEXTDC B2 BrisbaneNEXTDCQLD12 MW
12NEXTDC P1 PerthNEXTDCWA10 MW
13Dataspace Malaga Data CentreDataspaceWA10 MW
14NEXTDC A1 AdelaideNEXTDCSA5.0 MW
15Fujitsu North Ryde Data CentreFujitsuNSW4.8 MW

Only facilities whose operator publishes an IT capacity figure are ranked.

Figures published only in MVA (not ranked)

Capacity figures published only in MVA
ProjectOwner / operatorStateStageCapacity
Goodman MEL02 Building A, TruganinaGoodman GroupVICPlanning~180 MVA Grid connection
Goodman Project Atlas, Eastern CreekGoodman GroupNSWPlanning500 MVA Grid connection

These projects publish only a grid-connection figure in MVA, which is not a MW figure and is not ranked or added to totals.