CDC Marsden Park campus

CDC Data Centres · Marsden Park, New South Wales

The header graphic is a stylised illustration, not a photograph of this project.

Key facts

Owner / operator
CDC Data Centres
Location
Marsden Park, New South Wales (NSW)
Stage
Under construction
Capacity (as published)
504 MW IT / 720 MW total (approved); modification lodged to 743.5 MW
Expected start
Nov 2025 (early works)
Expected completion
Commissioning & handover Sep 2027 – Dec 2029
Investment value
EDC A$3,113,226,273 (NSW assessment report)
Builder / head contractor
Not named
Named contractors by trade
  • iCOST – embedded commercial (cost) support across delivery stages
  • Stantec – engineer – certified the NABERS embodied-emissions materials form in the SSD application (and energy details)
As published: iCOST – embedded commercial (cost) support across delivery stages; Stantec (engineer – certified the NABERS embodied-emissions materials form in the SSD application (and energy details))
Named suppliers
—
Tender / procurement status
CDC timeline: structure Jul 2026–Nov 2027; MEP & IT systems installation Feb 2027–Nov 2028. CDC held a 100+ partner supply-chain briefing (incl. electrical services, manufacturing)
Notes
Approved Nov 2025; 132/11kV on-site substation; Li-ion UPS + diesel generators.
Sources
Available to members — become a member
Last updated
2026-11-13
Updated regularly. Spotted a change? Let us know. Source citations are available to members — become a member.

Suggest an update to this project

Other projects in New South Wales

All 43 projects in NSW → · 43 operating facilities in NSW →