NEXTDC S4 Sydney – Phase 1

NEXTDC · Horsley Park, New South Wales

The header graphic is a stylised illustration, not a photograph of this project.

Key facts

Owner / operator
NEXTDC
Location
Horsley Park, New South Wales (NSW)
Stage
Under construction
Capacity (as published)
250 MW approved (SSD-63741210); NEXTDC states 365 MW total planned campus
Expected start
Mar 2026 (ground broken)
Expected completion
Mid-2027 (Multiplex)
Investment value
—
Builder / head contractor
Multiplex
As published: Multiplex (ECI then D&C)
Named contractors by trade
Electrical
Consultants
  • HDR – architect
  • Greenbox – architect
  • WT Partnership – quantity surveyor – certified the NABERS embodied-emissions materials form in the SSD application
As published: Heyday (Southern Cross Electrical, ASX:SXE) – electrical & comms works under limited LOA from Multiplex; architects HDR / Greenbox; WT Partnership (quantity surveyor – certified the NABERS embodied-emissions materials form in the SSD application)
Named suppliers
—
Tender / procurement status
Electrical LOA awarded Jun 2026; Multiplex states 'millions of dollars allocated to procurement from local suppliers'; prefabricated mech plantrooms & electrical switch rooms; on-site 330kV substation
Notes
Approved 24/12/2025. ~1,800 workers at peak. Heyday scope (stage 1): HV switching building, security ops centre, ancillary buildings and 2 of 4 multi-level data hall buildings (~60,000m2 GFA)
Sources
Available to members — become a member
Last updated
2026-11-13
Updated regularly. Spotted a change? Let us know. Source citations are available to members — become a member.