NEXTDC S7 Sydney (OpenAI MoU)
NEXTDC; OpenAI MoU (non-binding) · Eastern Creek, New South Wales
The header graphic is a stylised illustration, not a photograph of this project.
Key facts
- Owner / operator
- NEXTDC, OpenAI (MoU only)As published: NEXTDC; OpenAI MoU (non-binding)
- Location
- Eastern Creek, New South Wales (NSW)
- Stage
- PlanningPlanning (Prepare EIS)
- Capacity (as published)
- 612 MW (SSD description)
- Expected start
- First phase targeted H2 2027, subject to approvals
- Expected completion
- —
- Investment value
- ~A$7bn reported for the OpenAI/S7 plan
- Builder / head contractor
- —
- Named contractors by trade
- Moits – >1 million m3 bulk earthworks, detailed excavation, ~1.5km retaining walls, stormwater (for Multiplex) Civil
As published: Moits – >1 million m3 bulk earthworks, detailed excavation, ~1.5km retaining walls, stormwater (for Multiplex)- Named suppliers
- —
- Tender / procurement status
- Pre-approval; SSD lists 340 backup diesel generators, on-site substation
- Notes
- OpenAI arrangement is an MoU only.
- Sources
- Available to members — become a member
- Last updated
- 2026-11-13
Updated regularly. Spotted a change? Let us know. Source citations are available to members — become a member.
Suggest an update to this project
Other projects in New South Wales
- CDC Ashfords Road Data Centre, Gregadoo Gregadoo · 1.4 GW
- Mamre Road Data Centre Campus Kemps Creek · 1.2 GW
- IREN Redbank campus Gregadoo · 900 MW
- AirTrunk Kurri Kurri Data Centre Loxford / Kurri Kurri · 550.5 MW
- CDC Marsden Park campus Marsden Park · 504 MW
- STACK SYD01 Erskine Park Erskine Park · 450 MW
- AirTrunk SYD3 (expansion) Western Sydney · 400 MW
- Stockland Aldington Road Kemps Creek · 360 MW
- NEXTDC S4 Sydney – Phase 1 Horsley Park · 250 MW
- Macquarie Engineering & Technology Campus (METC) Macquarie Park · 200 MW
- Glendenning Road Data Centre (AWS-linked) Glendenning · 193.6 MW
- Davis Road Data Centre ('Project Blue Tongue') Wetherill Park · 180 MW