Wetherill Park Data Centre (2 Davis Road)
Stockland · Wetherill Park, New South Wales
The header graphic is a stylised illustration, not a photograph of this project.
Key facts
- Owner / operator
- Stockland
- Location
- Wetherill Park, New South Wales (NSW)Local government area: Fairfield City
- Stage
- PlanningPlanning (Prepare SEARs, SSD-153190740)
- Planning application
- SSD-153190740 (NSW State Significant Development)lodged 16 Oct 2026; applicant as stated on the register: Stockland Development Pty Limited
- Capacity (as published)
- 170 MW IT load
- Expected start
- —
- Expected completion
- —
- Investment value
- A$2.25bn estimated development cost (excl. GST) in the request for SEARs
- Builder / head contractor
- —
- Named contractors by trade
- —
- Named suppliers
- —
- Tender / procurement status
- —
- Notes
- One four-storey data centre building with demolition and site establishment works, an on-site substation and a transmission line (NSW Major Projects description). Scoping report published 16 Oct 2026. Separate from the Davis Road Data Centre ('Project Blue Tongue') at 3 Davis Road.Capacity detail: About 238 MW total capacity; 170 MW IT load (NSW Major Projects project description)
- Sources
- Original source links: available to members — request via contact
- Last updated
- 2026-11-15
Updated regularly. Spotted a change? Let us know. Original source links: available to members — request via contact. How we verify.
Suggest an update to this project
Other projects in New South Wales
- CDC Ashfords Road Data Centre, GregadooGregadoo · Up to 1.4 GW (Total facility)
- CDC Kemps Creek (third Sydney campus)Kemps Creek · 1.4 GW (Total facility)
- Mamre Road Data Centre CampusKemps Creek · 1.2 GW (Basis not stated)
- IREN Redbank campusGregadoo · Up to 900 MW (Total facility)
- NEXTDC S7 Sydney (OpenAI MoU)Eastern Creek · 612 MW (Basis not stated)
- AirTrunk Kurri Kurri Data CentreLoxford / Kurri Kurri · 550.5 MW (Basis not stated)
- CDC Marsden Park campusMarsden Park · 504 MW (IT load)
- STACK SYD01 Erskine ParkErskine Park · Up to 450 MW (Basis not stated)
- AirTrunk SYD3 (expansion)Huntingwood · 400+ MW (Total facility)
- Stockland Aldington RoadKemps Creek · Up to 360 MW (IT load)
- NEXTDC S4 Sydney – Phase 1Horsley Park · 250 MW (IT load)
- Macquarie Engineering & Technology Campus (METC)Macquarie Park · ~200 MW (Basis not stated)
- Glendenning Road Data Centre (AWS-linked)Glendenning · 193.6 MW (IT load)
All 48 projects in NSW → · 59 data centre facilities in NSW →