Operational / expansionNSW
DigiCo SYD1 Ultimo – expansion
DigiCo Infrastructure REIT · Ultimo, New South Wales
The header graphic is a stylised illustration, not a photograph of this project.
Key facts
- Owner / operator
- DigiCo Infrastructure REIT
- Location
- Ultimo, New South Wales (NSW)
- Stage
- Operational / expansionOperational – expansion (construction underway)
- Capacity (as published)
- Additional 52 MW IT load (SHAPE / DigiCo community project portal). The NSW Planning project summary for SSD-69637456 describes an increase in power consumption of 47.5 MW — figures differ.
- Expected start
- October 2026 (SHAPE / DigiCo community portal)
- Expected completion
- Forecast completion December 2028 (SHAPE / DigiCo community portal)
- Investment value
- A$800 million capital investment (SHAPE / DigiCo community portal)
- Builder / head contractor
- SHAPE Australia
- Named contractors by trade
- Electrical
- Heyday (Southern Cross Electrical) – D&C LV switchboards, busways, generators & UPS installation, containment, LV reticulation (20MW deployment, for SHAPE; Q2 2026) Power / generators
- Trivantage Manufacturing (SCEE) – 7 sets of generator & UPS switchboards, ordered by DigiCo subsidiary
Fire- Force Fire (SCEE) – D&C fire services: hydrants, sprinklers, detection, EWIS, water mist (for SHAPE); also demolition
Consultants- Lehr Consultants International – engineer (NABERS accredited) – certified the NABERS embodied-emissions materials form in the SSD application
As published: Heyday (Southern Cross Electrical) – D&C LV switchboards, busways, generators & UPS installation, containment, LV reticulation (20MW deployment, for SHAPE; Q2 2026); Force Fire (SCEE) – D&C fire services: hydrants, sprinklers, detection, EWIS, water mist (for SHAPE); also demolition; Trivantage Manufacturing (SCEE) – 7 sets of generator & UPS switchboards, ordered by DigiCo subsidiary; Lehr Consultants International (engineer (NABERS accredited) – certified the NABERS embodied-emissions materials form in the SSD application) - Named suppliers
- —
- Tender / procurement status
- —
- Notes
- Expansion of the existing SYD1 data centre at 390–422 Harris Street and 273 Pyrmont Street, Ultimo. The community portal (required under Condition C19 of the consent) states construction is underway, with two additional levels, a height increase of about 12 m, consent SSD-69637456, and the proponent named as HDI SYD1 Property Holdings Limited. The portal lists about 700 construction jobs.
- Sources
- Available to members — become a member
- Last updated
- 2026-11-13
Updated regularly. Spotted a change? Let us know. Source citations are available to members — become a member.
Suggest an update to this project
Other projects in New South Wales
- CDC Ashfords Road Data Centre, Gregadoo Gregadoo · 1.4 GW
- Mamre Road Data Centre Campus Kemps Creek · 1.2 GW
- IREN Redbank campus Gregadoo · 900 MW
- NEXTDC S7 Sydney (OpenAI MoU) Eastern Creek · 612 MW
- AirTrunk Kurri Kurri Data Centre Loxford / Kurri Kurri · 550.5 MW
- CDC Marsden Park campus Marsden Park · 504 MW
- STACK SYD01 Erskine Park Erskine Park · 450 MW
- AirTrunk SYD3 (expansion) Western Sydney · 400 MW
- Stockland Aldington Road Kemps Creek · 360 MW
- NEXTDC S4 Sydney – Phase 1 Horsley Park · 250 MW
- Macquarie Engineering & Technology Campus (METC) Macquarie Park · 200 MW
- Glendenning Road Data Centre (AWS-linked) Glendenning · 193.6 MW
- Davis Road Data Centre ('Project Blue Tongue') Wetherill Park · 180 MW