Key facts
- Owner / operator
- DCI Data Centers
- Location
- Eastern Creek, New South Wales (NSW)
- Stage
- Under construction
- Capacity (as published)
- DCI's July 2026 project update describes a 36 MW purpose-built facility as approved by Blacktown City Council in January 2021, and states that DCI was at that time seeking an additional SSD modification to increase capacity to 63 MW. Whether that modification has since been determined is not confirmed on the pages checked on 13 November 2026.
- Expected start
- —
- Expected completion
- —
- Investment value
- Approximately A$400 million (DCI, July 2026)
- Builder / head contractor
- MultiplexAs published: Multiplex (enabling works; that package is listed as completed)
- Named contractors by trade
- —
- Named suppliers
- —
- Tender / procurement status
- —
- Notes
- Sits alongside DCI's existing SYD01 facility at Eastern Creek. DCI says the project holds State Significant Development consent SSD-21342738 (1 September 2023) for a four-storey data hall building, ancillary office and supporting infrastructure. Its July 2026 update said Stage 1 (demolition) and Stage 2 (tank relocation) were nearing completion, with Stage 3 (data hall and substation) scheduled to start soon. Multiplex's project page states it has completed the early enabling works, including demolition of four industrial buildings, new stormwater tanks, and relocation of SYD01 water storage. Staging: Stage 1 demolition & Stage 2 tank relocation (Multiplex enabling works) nearing completion Jul 2026; Stage 3 data hall + substation to start; SSD mod to 63MW
- Sources
- Available to members — become a member
- Last updated
- 2026-11-13
Updated regularly. Spotted a change? Let us know. Source citations are available to members — become a member.
Suggest an update to this project
Other projects in New South Wales
- CDC Ashfords Road Data Centre, Gregadoo Gregadoo · 1.4 GW
- Mamre Road Data Centre Campus Kemps Creek · 1.2 GW
- IREN Redbank campus Gregadoo · 900 MW
- NEXTDC S7 Sydney (OpenAI MoU) Eastern Creek · 612 MW
- AirTrunk Kurri Kurri Data Centre Loxford / Kurri Kurri · 550.5 MW
- CDC Marsden Park campus Marsden Park · 504 MW
- STACK SYD01 Erskine Park Erskine Park · 450 MW
- AirTrunk SYD3 (expansion) Western Sydney · 400 MW
- Stockland Aldington Road Kemps Creek · 360 MW
- NEXTDC S4 Sydney – Phase 1 Horsley Park · 250 MW
- Macquarie Engineering & Technology Campus (METC) Macquarie Park · 200 MW
- Glendenning Road Data Centre (AWS-linked) Glendenning · 193.6 MW
- Davis Road Data Centre ('Project Blue Tongue') Wetherill Park · 180 MW