DC Info
Under constructionVIC

Vantage MEL1

Vantage Data Centers · Tullamarine, Victoria

The header graphic is a stylised illustration, not a photograph of this project.

Key facts

Owner / operator
Vantage Data Centers
Location
Tullamarine, Victoria (VIC)
Stage
Under construction
Capacity (as published)
64 MW critical IT
Expected start
—
Expected completion
—
Investment value
—
Builder / head contractor
Vantage (self-delivered per Prime)
Named contractors by trade
  • Prime – lead subcontractor: civil, electrical & communications, hydraulics CivilElectricalCommunications / ICTHydraulic
As published: Prime – lead subcontractor: civil, electrical & communications, hydraulics
Named suppliers
—
Tender / procurement status
—
Notes
On-campus 66kV substation. Prime scope confirmed: civil, electrical & communications and hydraulic works, in-ground to base build, as lead subcontractor; 66kV on-campus substation
Sources
Available to members — become a member
Last updated
2026-11-13
Updated regularly. Spotted a change? Let us know. Source citations are available to members — become a member.

Suggest an update to this project

Other projects in Victoria

All 30 projects in VIC → · 21 operating facilities in VIC →