Stockland Brooklyn Data Centre

Stockland · Brooklyn (413 Francis St), Victoria

The header graphic is a stylised illustration, not a photograph of this project.

Key facts

Owner / operator
Stockland
Location
Brooklyn (413 Francis St), Victoria (VIC)
Stage
Planning
Planning (DFP; decision deferred past 28 Nov 2026 election)
Capacity (as published)
~225 MW ultimate grid capacity (The Age); 250 MVA (AFR via Certified Strategic)
Expected start
—
Expected completion
—
Investment value
Stage one A$935m
Builder / head contractor
—
Named contractors by trade
—
Named suppliers
—
Tender / procurement status
Stockland: detailed design and contractor tender phase will follow approval; Tier 1 contractor intended
Notes
Reported: 96 rooftop chillers, 112 generators (The Age).
Sources
Available to members — become a member
Last updated
2026-11-04
Updated regularly. Spotted a change? Let us know. Source citations are available to members — become a member.

Suggest an update to this project

Other projects in Victoria

All 30 projects in VIC → · 21 operating facilities in VIC →