Operational / expansionWA
NEXTDC P1 Perth – Stage Two
NEXTDC · Malaga, Western Australia
The header graphic is a stylised illustration, not a photograph of this project.
Key facts
- Owner / operator
- NEXTDC
- Location
- Malaga, Western Australia (WA)
- Stage
- Operational / expansionOperational – expansion (Stage Two practical completion 1 Oct 2026)
- Capacity (as published)
- 10MW+ target IT capacity for the P1 facility (NEXTDC). NEXTDC's FY26 results presentation (27 Aug 2026) reported 5.5 MW built and 2 MW in progress. Multiplex announced practical completion of Stage Two on 1 Oct 2026, stating that the new 1,069 m² data hall doubled the facility's IT capacity; that release does not publish a separate MW figure for the stage.
- Expected start
- —
- Expected completion
- Stage Two practical completion 1 Oct 2026 (Multiplex)
- Investment value
- —
- Builder / head contractor
- Multiplex
- Named contractors by trade
- —
- Named suppliers
- —
- Tender / procurement status
- —
- Notes
- P1 is at 4 Millrose Drive, Malaga. Multiplex says it worked under an Early Contractor Agreement and delivered Stage Two on time and on budget alongside the operating Stage One facility. The FY26 figures above pre-date the 1 Oct 2026 completion announcement. Multiplex under Early Contractor Agreement; PC 1 Oct 2026; new 1,069m2 data hall; prefabricated risers/pipework; Multiplex 5th NEXTDC DC in 7 yrs
- Sources
- Available to members — become a member
- Last updated
- 2026-11-13
Updated regularly. Spotted a change? Let us know. Source citations are available to members — become a member.
Suggest an update to this project
Other projects in Western Australia
- Project Meridien South of Broome · 1 GW
- CDC Maddington campus Maddington · 150 MW
- NEXTDC P2 Perth East Perth · 20 MW
- CDC Hazelmere data centre Hazelmere