Under constructionWA
CDC Maddington campus
CDC Data Centres · Maddington, Western Australia
The header graphic is a stylised illustration, not a photograph of this project.
Key facts
- Owner / operator
- CDC Data Centres
- Location
- Maddington, Western Australia (WA)
- Stage
- Under construction
- Capacity (as published)
- 150 MW of IT capacity in CDC's Maddington Campus overview included in the City of Gosnells Metro Outer DAP papers (meeting 10 Sep 2025, DAP/25/02926). CDC's project page does not itself publish a MW figure. A later CDC announcement (12 Aug 2025) referred to a planned Western Australian campus of up to 200 MW of high-density capacity without naming Maddington in that release.
- Expected start
- Site preparation and early works Oct 2025; main works Dec 2025 (CDC project timeline)
- Expected completion
- First building operations scheduled to commence January 2027 (CDC project timeline); campus comprises four two-storey buildings when complete
- Investment value
- —
- Builder / head contractor
- BUILT
- Named contractors by trade
- Civil
- BY Group – bulk earthworks, enabling infrastructure, excavation (completed Mar 2026)
Other trades- WA Universal – crane hire/lifting (2x Comansa CML800 luffing tower cranes; 26 steel truss lifts)
- Jamel Industries – shopfitting/joinery (builder Built)
As published: BY Group – bulk earthworks, enabling infrastructure, excavation (completed Mar 2026); WA Universal – crane hire/lifting (2x Comansa CML800 luffing tower cranes; 26 steel truss lifts); Jamel Industries – shopfitting/joinery (builder Built) - Named suppliers
- —
- Tender / procurement status
- —
- Notes
- Industrial site off Bickley Road / Kenwick Road, Maddington. CDC says the development application was approved in September 2025 and that building fit-out commences in October 2026. The project page states four buildings up to 24 m high. Head contractor is not named on the CDC project page.
- Sources
- Available to members — become a member
- Last updated
- 2026-11-13
Updated regularly. Spotted a change? Let us know. Source citations are available to members — become a member.
Suggest an update to this project
Other projects in Western Australia
- Project Meridien South of Broome · 1 GW
- NEXTDC P2 Perth East Perth · 20 MW
- NEXTDC P1 Perth – Stage Two Malaga · 10 MW
- CDC Hazelmere data centre Hazelmere