NEXTDC B2 Brisbane – Stage 2

NEXTDC · Fortitude Valley, Queensland

The header graphic is a stylised illustration, not a photograph of this project.

Key facts

Owner / operator
NEXTDC
Location
Fortitude Valley, Queensland (QLD)
Stage
Operational / expansion
Operational – expansion (Stage 2 under construction)
Capacity (as published)
12 MW total planned IT capacity (NEXTDC / Multiplex); 6 MW built and 2 MW in progress as of NEXTDC's FY26 results (27 Aug 2026). Stage 2 doubles long-term IT capacity from 6 MW to 12 MW.
Expected start
—
Expected completion
Early 2027 (Bennett + Bennett project page)
Investment value
—
Builder / head contractor
Multiplex
Named contractors by trade
  • Superior Group – ceilings & partitions, external façade, data cages & cladding (~A$10m, for Multiplex) Other trades
As published: Superior Group – ceilings & partitions, external façade, data cages & cladding (~A$10m, for Multiplex)
Named suppliers
—
Tender / procurement status
—
Notes
Existing facility at 454 St Pauls Terrace, Fortitude Valley. Multiplex is delivering a new 1,400 m² data hall within the operating facility. NEXTDC's FY26 results presentation (27 Aug 2026) lists status as Operational, with 6 MW built and 2 MW in progress. Multiplex scope: extension + 1,400m2 new data hall; doubles IT from 6MW to 12MW
Sources
Available to members — become a member
Last updated
2026-11-13
Updated regularly. Spotted a change? Let us know. Source citations are available to members — become a member.

Suggest an update to this project

Other projects in Queensland

19 operating facilities in QLD →